Table outlining the key actions to implement during the operational phases planned for the Phlegraean Fields (2025)

Table 2 “Overview of key actions to implement during the operational phases” on page 5 of Annex 2 “Update of the operational phases and initial guidelines following the new alert levels” included in the Decree of the Head of Department No. 3236 of October 30, 2025 - "Approval of alert levels for the Phlegraean Fields volcano and initial operational guideline." 

Measures planned under ordinary circumstances:

▪  monitoring and scientific surveillance
▪  civil protection planning
▪  information, awareness-raising, and communication activities on risk and planning

Measure planned during the attention phase:

PHASE 1

▪  Intensification of monitoring and scientific surveillance activities
▪  Review and possible updating of civil protection planning
▪  Institutional information coordination
▪  Information activities for the population
▪  Training activities for operators

PHASE 2

▪  Further enhancement of scientific monitoring, surveillance, and assessment of the volcano's status
▪  Review and possible update of civil protection planning 
▪  Implementation of institutional information coordination
▪  Implementation of training activities for operators and institutional entities involved
▪  Implementation of information and communication activities
▪  Exercise activities

Measures planned during the pre-alarm phase:

PHASE 1

▪  Declaration of the national state of emergency
▪  Activation of the DiComaC according to the activities
▪  Activation of CAS for the population voluntarily leaving the red zone
▪  Application of measures in the area most affected by precursor phenomena
▪  Cultural heritage safety measures
▪  Evacuation of health and social-health facilities
▪  Evacuation of prisons
▪  Activities related to restrictions on tourist access and mass events
▪  Preparatory actions for the implementation of measures provided for the remaining part of the red zone

PHASE 2

▪  Full activation of DiComaC
▪  Implementation of all sector plans in the red zone, and in particular:
   ▪  Cultural heritage safety measures
   ▪  Evacuation of healthcare and social-healthcare facilities
   ▪  Evacuation of prisons
   ▪  Coordination and data exchange activities for the preparation of twinning arrangements

Measures planned during the alarm phase:

▪  Measures aimed at evacuating the population from the entire red zone